A manager asks when a fixed set of features will finish. What is the most empirical response?

Published
  1. Add estimates from unrelated teams as if directly comparable
  2. Promise an exact date without examining delivery data
  3. Forecast using evidence and explain uncertainty
  4. Refuse to discuss forecasts because Scrum forbids dates