A new Scrum Team asks how much work to select for its first Sprint. What should inform the forecast?

Published
  1. Available capacity, current understanding, and the Definition of Done
  2. The Product Owner's unilateral quota
  3. Every item in the Product Backlog
  4. A mandatory industry-standard velocity