A new Scrum Team asks how much work to select for its first Sprint. What should inform the forecast?
Published
- Available capacity, current understanding, and the Definition of Done
- The Product Owner's unilateral quota
- Every item in the Product Backlog
- A mandatory industry-standard velocity