A recurring external approval delay prevents the team from producing Done work. What should the Scrum Master do?

Published
  1. Exclude approval from Done without discussing the actual risk
  2. Help remove the organizational impediment
  3. Accept permanent unfinished Increments
  4. Assign blame during the Sprint Review