A stakeholder asks the Developers to add urgent work halfway through the Sprint. What should happen?
Published
- Reject any discussion until the next Sprint
- Accept every request automatically
- Discuss scope with the Product Owner without endangering the Sprint Goal
- Cancel the Sprint immediately