A stakeholder asks the Developers to add urgent work halfway through the Sprint. What should happen?

Published
  1. Reject any discussion until the next Sprint
  2. Accept every request automatically
  3. Discuss scope with the Product Owner without endangering the Sprint Goal
  4. Cancel the Sprint immediately