A stakeholder wants to change Product Backlog ordering. What is the appropriate route?

Published
  1. Assign the work directly to one Developer
  2. Discuss and persuade the Product Owner
  3. Reorder it secretly through direct database edits
  4. Cancel the Sprint independently

Comments — 0