A team improves a process during the Sprint rather than waiting for its Retrospective. Is this consistent with Scrum?
Published
- Yes; improvement is not restricted to the Retrospective
- No; all process changes must wait
- Only if stakeholders become Developers
- Only if the Sprint is restarted