A team meets its output forecast but stakeholders learn that the market need changed. What should the Sprint Review support?

Published
  1. Declare the original roadmap immutable
  2. Treat every market change as Developer failure
  3. Skip Product Backlog updates until annual planning
  4. Inspect the change and collaborate on useful adaptations