An item is partly complete at Sprint end and has not met the Definition of Done. What happens next?

Published
  1. It returns to the Product Backlog for future consideration
  2. It automatically becomes the top item next Sprint
  3. The Sprint remains open until it finishes
  4. It is demonstrated as Done if most tasks finished

Comments — 0