An item is partly complete at Sprint end and has not met the Definition of Done. What happens next?
Published
- It returns to the Product Backlog for future consideration
- It automatically becomes the top item next Sprint
- The Sprint remains open until it finishes
- It is demonstrated as Done if most tasks finished