Developers discover that a task is unnecessary to achieve the selected item and Sprint Goal. What should happen?
Published
- Erase the Sprint Goal
- Ask a stakeholder committee to approve every deletion
- Complete it anyway because planning is immutable
- Update the Sprint Backlog to reflect the learning