This website uses cookies to ensure you get the best experience.
Learn more.
Multiple Scrum Teams work on the same product. Which statement about the Definition of Done is correct?
Published
- The Product Owner can waive it for one team
- They must mutually define and comply with the same Definition of Done
- Each team may use incompatible completion standards
- Only the integration team needs a Definition of Done
Comments — 0
Sign in to comment