The Product Owner pressures Developers to skip a required security check to meet a forecast. What should Developers do?

Published
  1. Maintain the Definition of Done and discuss scope tradeoffs
  2. Skip it because product value always overrides quality
  3. Extend the Sprint without discussion
  4. Silently mark the work Done and test later